Blog · 13 November 2026 · 8 min read

User acceptance testing,getting the business to test and sign off

Who tests, with which scenarios, how to sort the feedback and what to write in the sign-off so the decision to accept is clear.

A white wireframe lectern holding an open ledger, with a rubber stamp raised above it and a few green lines, on a black background
Fig. 01A white wireframe lectern holding an open ledger, with a rubber stamp raised above it and a few green lines, on a black background

User acceptance testing is the moment when the people who will use the software try what has been delivered and say whether they accept it. In theory it is simple. In practice, three things come up often: testers warned the day before, feedback that mixes bugs with new requests, and a sign-off document signed without anyone really knowing what they are accepting.

I have already described how I run acceptance testing up to go-live: the test log, end-to-end journeys, the checklist. This note is about the other side of the table, the users. Who should test, how to prepare them, how to sort what they report, and what to write in the sign-off so the decision is clear.

01User acceptance testing means the business decides

The French Wikipedia page on acceptance testing separates the stages well: factory acceptance, run by the supplier and closed with a report signed by both sides, then the fitness check at the client's site, then a period of regular service on a pilot site. User acceptance testing sits in the middle. The supplier has already tested what it understood; now the client checks that it meets the actual need.

Mike Clayton, who trains project managers, puts it well in his video on user acceptance testing: specialist testers know how the system is supposed to work, so they have to force themselves to do unexpected things. Users simply do what feels natural. He makes another point I agree with: UAT is not there to hunt for bugs, it is there to confirm that no important ones remain and that the product is ready. It ends with a sign-off.

That is why I never let the project team test alone what it has built, me included. I prepare, I run the sessions, I sort the feedback. The decision belongs to the business.

02Choosing the testers and preparing them

The first choice is the person who will sign. I have them named in the test plan, in writing, before the first session. It is not necessarily the person highest up: it is the one who can say yes on behalf of the people who will use the tool, and who will be available on the planned dates. In a Scrum team, the Scrum Guide makes the Product Owner accountable for the value of the product and notes that they may represent the needs of many stakeholders. I use that as a starting point, not as an excuse to bring nobody else in.

Then the testers. I look for people who do the work every day, not representatives. Two or three per business area is often enough. Above all, I check that time is blocked in their diaries and agreed with their manager. Acceptance testing done "on top of everything else" happens on a Friday evening, half-heartedly.

Writing the scenarios in their words

I do not send testers a test log written by the project team. I spend an hour with them and ask them to describe a normal day, then a difficult one: the order that arrives twice, the credit note at month end, the customer who changes address after confirming. Each story becomes a scenario, with its starting data and the expected result, written before the test.

The specification is the reference, but it has to be a precise one. For a client, on an integration between an ERP and an online shop, the integration specification changed at almost every meeting. I versioned it, and acceptance testing was done against a given version. Without that, every disagreement turns into a debate about what was said in a meeting.

A supported session, not a file sent by email

I prefer to bring testers together, in a room or on a video call, on an environment close to production, with data that looks like the real thing. I stay to unblock an access issue, note a gap, rephrase a comment. Testers do not have to fill in a tracking tool they have never seen: they tell me what they see, and I write it down with them.

Acceptance testing sent out by email rarely comes back complete. You get three screenshots with no context and a "looks fine overall". You save a lot of time by being in the room.

03Defect or change request: sorting feedback before it piles up

This is where acceptance testing gets bogged down. A tester reports "the filter by region is missing". Is it a defect, because it was planned, or a change request, because nobody asked for it? Both are legitimate, but they are handled differently: a defect is fixed within scope, a change request is estimated and scheduled.

I sort every piece of feedback the same day, with one simple rule: we look at the version of the specification being tested. If the behaviour is described there and the software does something else, it is a defect. If it is not there, it is a change request, and I put it on a separate list so it does not get lost. Then each defect gets a level: blocking, to fix before go-live, or acceptable as it is.

This grid comes from my own tools. My content machines use a three-colour check that I describe in the note on my AI content machine. Red: a single point is enough to block. Amber: it may be acceptable, but the article only goes out with a written justification for each point. And a check that did not run counts as red, never as green. Carried over to acceptance testing, amber becomes the reservation, and the scenario nobody had time to run stays open.

04The UAT sign-off: what it contains and who signs it

The sign-off is the written record of the decision. In French public procurement, the general terms for public ICT contracts give a vocabulary I find useful even outside that setting. After verification, the buyer can accept the deliverables if they recognise them as compliant, defer by a reasoned decision, accept with a reduction in the amount paid in proportion to the defects found, or reject. Four outcomes, not two.

In a private contract, the contract sets the rules, and I am not a lawyer. But keeping those four outcomes in mind avoids the false choice between "everything is perfect" and "we sign nothing". Accepting with reservations is not a failure, as long as the reservations are written down.

The template I use

My sign-off fits on one or two pages:

  1. The scope tested and the version delivered, with the version of the reference specification.
  2. The dates, the environment and the names of the testers.
  3. The list of scenarios run, with their results, and those that could not be run.
  4. The remaining defects, ranked blocking, to fix before go-live, acceptable.
  5. The reservations: for each one, a sentence saying why it is accepted, who will clear it and by when.
  6. The list of change requests noted, taken out of scope.
  7. The decision (accepted, accepted with reservations, deferred, rejected), the date and the signature of the person named at the start.

Point 5 is the one I would urge you to get right. A reservation with no owner and no date is a defect you have decided to forget.

05What user acceptance testing does not replace

It does not replace usability testing. The Nielsen Norman Group describes a usability test as a session where a facilitator asks a participant to perform tasks and observes their behaviour, and recommends five participants to uncover most of the common problems. The aim is to see whether people manage, not to validate a need. The GOV.UK Service Manual also asks teams to test the usability of a service as well as its technical parts. If you discover during acceptance testing that a screen makes no sense, it is late. I would rather see it on a clickable prototype before development.

Nor does it settle a disagreement about the need. If the business discovers during testing that it wanted something else, the problem goes back to scoping. Acceptance testing makes it visible, which has value, but it does not fix it.

And it has a cost. Testers have their own jobs, and serious acceptance testing takes several half-days of their time. When an outside supplier delivers, you also need to agree in advance who fixes what and how quickly, which I cover in the note on working with an IT services firm. If nobody can be freed up, I would rather move the date than get a sign-off nobody believes in.

I apply the same rule to myself. My articles are published with a "to review" status, and I read them myself on the public page, not in the editing form, before switching them to "Reviewed". When a proofreader gave me feedback on a pipeline, I turned it into written rules rather than corrections made by hand. It is the same idea as a well-kept reservation: the feedback becomes a rule, and it does not come back.

06Where to start before your next round of testing

If a delivery is coming up, do two things this week. Name in writing the person who will sign off, and block time for acceptance testing in the diaries of two or three business testers. The rest, scenarios, sessions and the sign-off template, can be built in a few days after that.

I prepare and run this kind of acceptance testing in my project direction work. If you are a few weeks from a delivery and the testing worries you, we can talk about it.

Frequently asked questions

Who should prepare the UAT sign-off document?
Usually the project manager or the supplier drafts it, because they hold the list of scenarios and defects. But the person who signs to accept is the client, and more precisely the person with the authority to say yes on behalf of the business. I have that person named in the test plan from the start. If you only find out who it is on the day of sign-off, the whole discussion starts again.
What goes into a UAT sign-off?
The scope tested and the version delivered, the dates and the environment, the list of scenarios with their results, the remaining defects ranked by severity, the accepted reservations with an owner and a date for each, then the decision itself (accepted, accepted with reservations, deferred or rejected) and the signature of the person making it. I add nothing else. A sign-off you can read in five minutes gets signed far more easily than a thirty-page file.
Can the project manager or Product Owner do the user acceptance testing?
They can organise it, run the sessions and take part, but I never leave the decision to them alone. They know too well what was built, so they test the expected path. Business users do whatever feels natural, and that is where the real gaps show up. In a Scrum team the Product Owner represents the stakeholders, which is no reason not to bring a few of them in for acceptance testing.
How does user acceptance testing work in practice?
For me, in four stages. We choose the testers and write the scenarios with them, based on their real work. We hold supported test sessions on an environment close to production, with realistic data. We sort every piece of feedback, defect or change request, as it comes in. Then we write the sign-off with the decision and the reservations, signed by the person named at the start.

Sources

  1. 01Wikipedia, Test d'acceptation (in French)
  2. 02Mike Clayton (Online PM Courses), Software Testing Process Guide: What is User Acceptance Testing - UAT?, YouTube
  3. 03Scrum Guides, The 2020 Scrum Guide
  4. 04Légifrance, Order of 30 March 2021 approving the general administrative terms for public ICT contracts (in French)
  5. 05Nielsen Norman Group, Usability (User) Testing 101
  6. 06GOV.UK Service Manual, Quality assurance: testing your service regularly