A two-line request, "a brochure site with a customer area and a link to the ERP", and a question: how long, how much? Many web project estimates start like this. The person answering under pressure gives a number. The person hearing it remembers it. Three months later, that number has become a promise nobody really made.
I have been running tech projects for twenty years, and my engagements start with a few days of diagnosis before anything gets built. I haven't found any other way to estimate a project without fooling myself. Here is how I go about it, what I always add to the estimate, and what the method doesn't solve.
01Why web project estimates go wrong
People tend to think projects slip a little, everywhere, all the time. The numbers say something else. Bent Flyvbjerg and Alexander Budzier studied 1,471 IT projects: the average cost overrun was 27%, but one project in six overran its budget by 200% on average and its schedule by almost 70% (Flyvbjerg and Budzier, Harvard Business Review). The danger comes from the project that spins out of control, far more than from the average.
Two causes come up in Flyvbjerg's work on forecasting: optimism (we picture the scenario where everything goes well) and strategic misrepresentation (we underestimate, sometimes knowingly, to get the project approved) (Flyvbjerg, Project Management Journal). In a web project I would add a third, more mundane cause: we estimate a sentence, not a scope. "Link to the ERP" can mean a daily export or real-time sync of stock, catalogue and orders. Those are not the same project.
02Break it down before you estimate it
I don't estimate what I don't understand. The UK government's Service Manual puts it well: before committing to build, you need to understand the problem, the users and the technical or legal constraints, and reframe any solution handed to you in advance as a problem to solve, agreeing what is not part of it too (GOV.UK Service Manual, discovery). In UK government, that phase typically lasts 4 to 8 weeks. For a medium-sized site or app, a few days are often enough, but the principle holds.
How I break a project down, step by step
- I restate the request as a problem: who uses it, to do what, and what is not part of the project. The list of what we won't do matters as much as the other one.
- I list the building blocks: pages and templates, features, content, integrations, accounts and permissions, analytics, go-live.
- I break each block down until a piece fits in a few days of work. Beyond that, the estimate becomes a guess.
- I flag the grey areas: anything that depends on a third party (an ERP vendor, a host, an internal team) or on a decision not yet made.
- I have each piece estimated by the person who will do it.
That last point comes from the Scrum Guide: backlog refinement breaks items down into smaller, more precise ones, and the developers who will do the work are responsible for sizing them, with the Product Owner helping them understand the trade-offs (Schwaber and Sutherland, The Scrum Guide). An estimate given by someone who won't do the work is an opinion. I have written up a fuller method for scoping a digital project in one week and for writing a website specification people actually read.
03A range, not a number
A single number gives false precision. I prefer a range, together with what makes it move.
A simple method helps a lot: three-point estimation. For each piece you note three durations: optimistic (everything goes well), most likely, and pessimistic (what could reasonably go wrong, short of disaster). The most common variant weights the most likely value: (optimistic + 4 × most likely + pessimistic) / 6. The arithmetic matters less than the conversation it starts. When the gap between optimistic and pessimistic is huge on one piece, that is where to dig before committing.
Compare with projects that were actually delivered
Flyvbjerg offers a remedy for optimism: reference class forecasting. You base the estimate on the actual results of a set of comparable projects, rather than on the scenario imagined for this one (Flyvbjerg, Project Management Journal). The outside view against the inside view.
I apply the same idea to my own content machine, the one that writes this blog. The number of words, headings and questions in an article isn't decided by feel: the brief calculates it from written limits and, depending on the machine, from the length of pages already ranking or from what has already been published. It is a small reference class. Without limits, generated text bloats.
For a web project, the reference is your past projects: how long the last site, the last integration, the last round of testing really took. If you haven't recorded it, start now, because no other estimating data comes close.
04What I always add to the estimate
The forgotten lines are always the same. In my view they belong in every estimate, even when nobody asks for them.
- Acceptance testing: writing test cases, running them, fixing, running them again. It involves the supplier and the people signing off, so it involves diaries.
- Content: copy, images, translations, migrating what exists. A site that is ready without content is not ready.
- Integrations: I treat them as the most uncertain line in the project.
- Go-live: redirects, domain, analytics, checking the public page.
- Back and forth: every sign-off meeting, every version of the mock-up.
On integrations, I learnt two things without looking for them. On an integration between an ERP and an online shop, the specification changed at almost every meeting; I evolved it version after version so everyone was talking about the same document (specification version control). An estimate that doesn't say which version it covers isn't worth much. And a simple mix of units between two tools, centimetres on one side and millimetres on the other, can distort a whole rendering. These problems don't show up in the estimate. You pay for them during the project.
Checking has a cost too, and it is easy to forget. At Moonworkers, my own company, the free calculators on the site were checked one by one against the official tools, and an oracle written from HMRC's texts replayed 896 contribution cases and found four one-penny errors caused by a rounding rule (testing a calculation with an oracle). That work appears on no mock-up. It still has to be in the estimate.
05What the method doesn't solve
It doesn't remove uncertainty, it makes it visible. A wide range often disappoints someone who wanted a number, and you have to accept that conversation at the start rather than at the end.
It also costs time before you begin. Paying for a few days of scoping to get an estimate is an investment some people refuse, especially on a small project. For a site of a few pages with no integration, I wouldn't recommend it: a simple estimate is enough. The UK manual says as much for the next phase: you prototype the parts you think will be hardest first, and you only move on to building once you are confident you have the budget and the people (GOV.UK Service Manual, alpha). If nothing is hard, there isn't much to prototype.
Finally, no estimate survives a scope that changes without being re-estimated. When a date can't move, what taught me most was my early career in audiovisual production: you fix the date, the budget and the quality, and the scope adjusts, as I explain in a piece on planning a project with a fixed deadline. The estimate is then tracked week after week, with project budget tracking that compares plan with actuals.
06Where to start on Monday
Take your next project and do three things before you give a number. Write one page on what the project does and what it doesn't. Break it into pieces of a few days, and have each one estimated in three points by the person who will do it. Then find the actual duration of your last two or three comparable projects and look at the gap with what you estimated back then. The gap is often uncomfortable, which is exactly what makes it useful.
If you would like an outside view of an estimate or a scoping exercise before you commit, that is the kind of short engagement I do: the SLX Management services and a few past projects give an idea of how I work. Happy to talk it through.