A go-live with a fixed date often means a week of nerves, then an evening where everyone stares at the same screen hoping nothing breaks. I think that stress rarely comes from the technology. It comes from what was never written down: the order of actions, the person allowed to say stop, and what happens if things go wrong.
My content machine publishes to production every day, and I have borrowed the rules that hold it together for go-live day. Here is how I prepare a go-live so that it feels like a rehearsal: the cutover plan, the rollback, the go / no-go and the first hours. Acceptance testing already has its own article.
01What makes a go-live stressful
When I look at what worries a team before a cutover, I nearly always find the same gaps. Nobody knows exactly in what order things will happen. The rollback exists "in theory". The decision to launch is made out loud, at the last minute, by whoever talks loudest. And after launch, everyone goes home assuming someone else is watching.
The second factor is the size of the change. The GOV.UK Service Manual recommends deploying often and in small changes, and planning ahead for what to do if a smoke test fails. The work of DORA, Google Cloud's research programme, points the same way: it measures the share of deployments that need immediate intervention, and notes that smaller changes are easier to recover from.
A big end-of-project cutover is sometimes unavoidable: a new business tool, a complete redesign, a change of hosting. In that case I cannot make the change small. I can, however, make the day predictable.
02Writing the cutover plan hour by hour
The cutover plan is the document that says what happens on the day, line by line. I start it as soon as the date is set, not the night before. It often begins before the day itself, with a freeze on data entry or an announcement to users, and ends after launch, with the watch period.
I started out in audiovisual production, where you hold a team and a schedule to a date that does not move. What I kept from it: when the date is fixed, everyone needs to know what time they step in and what is expected of them. That is what the cutover plan is for.
The columns I put on every line
I keep a simple template that I copy from one project to the next. Every line of the plan has five columns:
- The planned time.
- The action, in one sentence.
- The owner, a name rather than a team.
- The check that proves it is done.
- What to do if it fails.
The first three lines of a plan often look like this:
- 6pm, freeze data entry in the old tool, by the business owner; check: message sent and read-only access confirmed; if it fails, postpone the cutover.
- 6.30pm, full production backup, by the technical lead; check: backup present and a sensible size; if it is missing, do not move on.
- 7pm, deploy the new version; check: status page and smoke test green; if it fails, first step of the rollback.
The "If it fails" column is the one people forget most. Yet it is the one that stops the improvising: every line already says what to do when it goes wrong.
This document will change during the weeks of preparation. On an integration between two tools, I watched a specification change at almost every meeting; I versioned it so that everyone was talking about the same document. I do the same with the cutover plan: a version number, a date, and a single copy that counts on the day.
For a site whose URLs change, I add the steps described in Google Search Central's guide to moving a site: make changes one after the other rather than all at once, and set up server-side permanent redirects, generally kept for at least a year. The detail on redirects is in my article on hosting migration.
03Deciding on the rollback before the day
The rollback is decided in a calm moment. On cutover night, with a tired team and a client waiting, nobody makes a good decision about how to go back. So I write three things in advance: who decides to roll back, until what time it is still possible, and how it is done.
The cut-off time matters more than people expect. Once users have started entering data into the new tool, going back to the old one means losing or re-entering that data. Past that point, you fix forward. I would rather everyone has heard that beforehand.
Some platforms make rollback almost instant. This site runs on Vercel, and its Instant Rollback documentation explains that you go back to a version that has already been built. It also warns about two traps: environment variables changed since then do not come back, and automatic assignment of the production domain is switched off until you promote another deployment. A fast rollback is still a rollback you need to understand.
Vercel also shows, in a video demonstration of its command line, how to find the first faulty deployment by comparing a healthy URL with the production URL, before pointing the domain back at the last version that worked. What I mainly take from it is the order: first find where it broke, then go back.
When going back is not possible, say so. Some data migrations cannot be undone. In that case the plan admits it, and the rehearsal on a copy of production becomes the only real safety net.
04The go / no-go, a written decision with criteria
The go / no-go is the moment you decide whether to launch. I prepare it like the gate in my content machine: a list of criteria set in advance, and a named person who is allowed to say no. My machine refuses to publish an article while any check is red, and when an article cannot pass honestly, it drops it with a note rather than forcing it through. I think that is a good rule for a cutover too.
My criteria look like this:
- Acceptance testing is signed off, with the list of accepted defects and who owns each one.
- The procedure has been rehearsed end to end on a recent copy of production.
- Today's backup exists, and restoring it has already been tested.
- The rollback is written down, with its cut-off time.
- The people on watch and on support are available and reachable.
A criterion we could not check counts as a failure. That is the rule in my tools: a check that did not run gives a red, never a default green. Saying "no-go" the day before costs a date. Launching on a doubt can cost much more, and it is exactly the kind of risk you want to have logged in the risk register well ahead of time.
If you are still in acceptance testing, my acceptance testing and go-live checklist and my article on user acceptance testing and sign-off cover what comes before this moment.
05The first hours after launch
A go-live is not over when the deployment says "successful". I always plan a watch window, with names and times, like the rest of the plan.
What I look at, in order
- The public page, seen as a visitor: private browsing, no team session, a form submitted all the way through.
- Error logs and alerts, on the new version and on the feeds connected to it.
- The first real usage: first orders, first sign-ups, first exchanges between tools.
- Feedback from support, with someone who knows where to escalate a problem.
The first point comes from a lesson on a project. I saw a site that looked fine to the logged-in team and was broken for visitors, because of a cache. Since then, my content machine checks every article on its public page after publishing, and I do the same after a cutover.
Another way to reduce the risk, when the tool allows it, is to open up gradually. Vercel's Rolling Releases first send the new version to a small fraction of users, then promote it to all traffic when you are ready. That is not possible on every project (a business tool rarely changes for only half of its users), but when it is, I prefer it.
There is a limit to all this: a cutover plan does not replace serious acceptance testing, and it takes preparation time that tight schedules have not always allowed for. On a small brochure site, a light version is enough. I keep the full plan for cutovers where a mistake touches data or money.
06Where to start for your next go-live
If your date is a few weeks away, I would start with three simple steps. Open a cutover plan document with the five columns, and fill it in even if it is incomplete. Write one sentence saying who decides on a rollback and until what time. Then set the date of the rehearsal on a copy of production, before you set anything else.
On this site, every push to the main branch redeploys production. My machine prepares everything and never pushes: I push, after reading it through. It is a small rule, but it sums up what I am after on go-live day, a single person deciding, at a moment they chose.
If you would like an outside view of your plan, that is the kind of scoping I do on short engagements, and you can see the sort of projects I take on in the portfolio. Happy to talk it through.