Managing a digital project for a major brand,what I pin down first

On a major brand campaign, the real schedule is the sign-off schedule. Here is what I pin down before the first mock-up.

A white wireframe maze seen from above on a black background, crossed corner to corner by a glowing green path
Fig. 01A white wireframe maze seen from above on a black background, crossed corner to corner by a glowing green path

From a distance, a digital project for a major brand looks like any other web project: a campaign site, a few landing pages, some content, paid media to bring people in. Up close, it is a different thing. There is a launch date that won't move, one or more agencies, and a lot of people who sign off: the brand team, legal, procurement, the IT department, sometimes international markets.

I started my career in video production, where you hold a budget, a schedule and a crew against a broadcast date that is not up for negotiation. Today I run digital projects on my own. I have worked on a project for a major brand I won't name. What I took from it comes down to a few scoping rules, which I set before the first mock-up.

01What changes when the brand is big

The technology is rarely the problem. A campaign page is still a page. What changes is the number of people with a say, and the fact that each of them sees the project from one angle: the brand team looks at the message, legal at the small print, IT at hosting and security, procurement at the contract.

Nobody is wrong. But if everyone signs off at their own pace, the production schedule becomes fiction. Agencies know this: their calendar assumes feedback arrives on the agreed dates, and that is where things slip most often.

The person running the project, on the brand side or alongside it, has to hold the whole thing together. I have written elsewhere about coordinating several suppliers on one project; on a major brand campaign, the difficulty moves from the suppliers to the internal sign-off chain.

02Map the sign-off chain before the schedule

My first deliverable is not a backwards schedule. It is a single page that says, for each type of deliverable, who approves it, in which order, within how many working days, and who decides when people disagree.

The questions I ask in the first week

  • Who has the final word on the message and the visuals?
  • Does legal review every page, or only the terms and the rules of a competition?
  • Does IT impose a host, a security audit or a lead time for go-live?
  • Do we need versions in other languages, and who approves them?
  • Who can say "we launch" on the day, and who can say "we stop"?

Once the chain is written down, I turn it into durations. If legal needs five working days and the brand wants two rounds of changes, that is ten days that are not production. Putting them into the schedule from the start changes the conversation with the agency, and makes the dependencies between tasks in a web project visible.

HubSpot's video on planning a campaign puts it simply: each phase of the schedule should have a clear deliverable, and when you work as a team, one section of the plan is there to spot gaps in responsibilities. On a major brand project, those gaps almost always sit between two departments that each thought the other was approving.

03A fixed date, a scope that can flex

On a campaign, the date is often the only thing that cannot move: a media booking, an event, a product release. Video production taught me a simple rule. When the date is fixed, the scope is what has to give, not the quality and not the team's nights.

So at the scoping stage I separate what must be live on launch day from what can follow a week or two later. A form, an English version, a secondary animation can often wait. The main message and the path to the action cannot.

Second rule: the reference document gets versioned. On an integration between two systems, I saw a specification change at almost every meeting. The only fix I know is to evolve it version by version, with a number and a date, so everyone is talking about the same text. On a campaign, the same goes for the brief, the site map and the content list.

Third rule: reporting goes out on its own. I prefer a short written update sent every week, and a steering committee that actually decides, to a dashboard nobody opens. The committee is not there to discover progress. It is there to settle what the team cannot settle alone.

04Get decisions made on comparable options

The point where a major brand project most often bogs down is creative sign-off. A single proposal goes round, everyone adds a comment, and the design turns into a compromise nobody really chose.

What has worked for me is showing several directions at the same level of finish. If one option is polished and the others are sketches, the decision is made in advance, and that is not a decision. With two or three comparable directions, the discussion is about substance.

The Nielsen Norman Group calls this parallel design: producing several alternative designs at the same time, quickly and on a few key pages only, then keeping the strongest parts of each. Their argument is that it stops you fixing on a single solution too early. On the project management side, I add one constraint: before the presentation, we agree who chooses and on what criteria.

05Cookies, accessibility, rights: deal with them before the final design

Three subjects often turn up too late, at acceptance testing, when they actually change the design.

Cookies and media pixels

A campaign lives on measurement: ad network pixels, analytics tags, share buttons. The CNIL, France's data protection authority, points out that these trackers, apart from the strictly necessary ones, require the user's prior consent, that refusing must be as easy as accepting, and that the site publisher and the ad networks can be joint controllers. In practice, I ask the media agency to list every planned tag, its purpose and its provider before the consent banner is designed.

Accessibility

In France, the digital accessibility obligation does not only cover the public sector. The RGAA framework states that it also applies to companies with at least 250 million euros of turnover in France, averaged over three financial years, and that it covers websites, intranets and mobile apps. Many major brands fall into that group. Contrast, video subtitles, keyboard navigation: I would rather see these points in the creative brief than in the list of last-minute fixes.

Rights

Photos, music, voiceover, typefaces: the duration and territory of use get checked before go-live, not after. I am not a lawyer and I don't replace the legal team. My job is to make sure the question was asked in time and that the answer is written down.

06On launch day, check as a visitor would

On launch day, the worst case is not the visible outage. It is the site that looks fine to the whole logged-in team and is broken for visitors. I have seen it happen on a site: the team saw the right version, the public a cached one.

Modern hosting platforms serve pages through a delivery network. Vercel's documentation explains that this network caches pages and files close to visitors to speed things up and take load off the origin server. That is very useful on launch day, when traffic arrives all at once. It also means that what you see, logged in, is not necessarily what the public sees.

My launch check

  1. Open every key page in a private window, on a phone and on a laptop, off the company network.
  2. Refuse cookies, then check that the page works and that no measurement tag fires.
  3. Follow the main journey to the end: form, confirmation, email received.
  4. Check the links coming from media (campaign parameters included) and the share links.
  5. Write down the time, what was checked and by whom, in the same document as everything else.

The full list I use for a go-live is in my acceptance testing and go-live checklist.

07Where to start on your next campaign

If you are launching a campaign in the coming weeks, I would start with one thing: write the sign-off chain on a single page, with durations, and have every department involved read it. It is a short document, and it is often the one that is missing.

One limit, to be honest. I work alone. I can scope, run and check a campaign build, but I don't do pure graphic production or long-term media management: on a campaign that runs for months, the agency and its teams are still needed. You can see the kind of projects I take on in my portfolio of missions, and what I offer on the digital project management services page. If your situation looks like this one, we can talk it through.

Frequently asked questions

What does a digital project manager do on a major brand campaign?
They hold together what each party only sees in pieces. I map the sign-off chain, keep the schedule and budget, get decisions made at the right level and check what goes live. The role replaces neither the agency's creative work nor the brand's decisions. The job is making sure decisions arrive on time and are written down.
How does an advertising agency work on this kind of project?
Usually the agency owns the creative idea and its production, sometimes with partners for development, video or media buying. On the brand side, several departments sign off. I don't speak for agencies, but working with them taught me one thing. The schedule they propose holds if feedback comes back on the agreed dates. That is usually where things slip.
How do you run a project well when lots of people need to approve it?
I start by writing down who approves what, in which order and within how many days, before setting production dates. Then I gather feedback into a single document per stage, version that document, and keep the steering committee for the calls the team cannot make alone. A written record of decisions after each meeting stops the same debate coming back.
Does a major brand have to make its campaign site accessible?
In France, the digital accessibility obligation applies to companies above a turnover threshold for business done in France, set by law and restated in the public RGAA framework. A campaign site published by such a company is an online service like any other. So I raise the question at the scoping stage, with the legal team, rather than during acceptance testing.

Sources

  1. 01HubSpot Marketing, How To Create a Marketing Campaign (FREE Template) (YouTube video)
  2. 02Nielsen Norman Group, Therese Fessenden, 3 Design Processes for High Usability: Iterative Design, Parallel Design, and Competitive Testing
  3. 03CNIL, Cookies and trackers: what does the law say? (in French)
  4. 04French government digital agency (DINUM), RGAA: scope of the accessibility obligation (in French)
  5. 05Vercel, Vercel CDN Cache (documentation)